Mesyuarat Pertama Penggal Keempat Dewan Negeri Selangor Tahun 2021
23 Ogos 2021 hingga 27 Ogos 2021, 30 Ogos 2021, 1 September 2021 hingga 3 September 2021 dan 6 September 2021
105) PROJEK AIR SELANGOR
Tahun: 2021
Sesi: 1
Isu: Infrastruktur & Kemudahan Awam
Adun: Y.B. Tuan Rajiv A/l Rishyakaran
Kategori: Bertulis
Sub Soalan
-
Senaraikan semua projek menambahbaik sistem bekalan air oleh Air Selangor untuk tahun 2020 dan 2021.
Berikut adalah senarai projek penambahbaikan sistem bekalan air pada tahun 2020 dan 2021.
Bil. Projek 2020 Kos Projek (RM Juta)
Status 1. Proposed water supply to Kg. Org Asli Bkt Kechil, Kuala Langat & Kg Org Asli Bkt Lagong, Gombak 0.5 Siap 100% 2. Proposed Improvement Work in Jalan Ulu Klang and Jalan Ampang 0.9 Peringkat pembinaan (Jadual 70%; Sebenar 67%) 3. Proposed Upgrading and Distribution Works for Low Water Pressure Areas in Klang Region (Sg Kandis and Jalan Kebun Area) 4.9 Peringkat pembinaan (Jadual 59.98%; Sebenar 49.92%) 4. Design and Build for Proposed Upgrading and Distribution Works for Water Stress and Low-Pressure Area in Petaling Region – Taman Wawasan 2.7 Peringkat pembinaan (Jadual 82%; Sebenar 40%) 5. Design And Build for Proposed Upgrading & Distribution Works for Water Stress And Low Pressure Area In Gombak Region – Bukit Lela Reservoir 2.8 Peringkat pembinaan (Jadual 53.70%; Sebenar 33.50%) 6. Improvement Works to Sg Lolo/Pangsoon WTP Supply Area [Phase 1] 8.8 Peringkat pembinaan (Jadual 68%; Sebenar 28%) 7. Proposed Re-activation of Bandar Sultan Suleiman 4 (BSS 4) 1 Mg Elevated Water Tank and Pressure Improvement Works at Kg. Sg. Sireh and Flat Sri Perantau 2.2 Peringkat pembinaan (Jadual 41%; Sebenar 17%) 8. Proposed Upgrading and Distribution Works for Low Water Pressure Areas in Klang Region (Kampung Lombong) – Peringkat penilaian tender 9. Proposed Improvement Works to Sg Lolo and Sg Pangsoon WTP Supply Areas (Phase 2) – Peringkat penilaian tender 10. Proposed Pipe Reticulation Improvement Works in Kg Sri Aman, Petaling – Peringkat penilaian tender 11. Proposed Improvement Works at Lipat Kajang Reservoir – Akan ditender pada bulan Ogos 2021 12. Proposed Construction of New Pump House at Batu Estate Reservoir, Kuala Lumpur – Akan ditender pada bulan Ogos 2021 13. Proposed pipe reticulation improvement works in Labu Lanjut, Sepang – Akan ditender pada bulan Ogos 2021 -
Apakah kos setiap projek?
Seperti jawapan di atas (a)
-
Apakah tahap kemajuan projek sekarang berbanding sasaran kemajuan?
Seperti jawapan di atas (a)